September 12, 2012
SUBJECT: Edgewater Pedestrian Safety Improvements
Project Limits: Edgewater Street from Kingwood Avenue to Patterson Avenue
Status Report No. 17
This update provides a schedule of anticipated construction to be performed within the next
couple of weeks on the Edgewater work in West Salem. Typically construction will occur
during daytime hours from 7 a.m. to 7 p.m. Nighttime work is not anticipated for this reporting
period. Contractor anticipates construction to resume on the remaining ADA ramps and curb
extensions mid September.
Week of September 10—September 14, 2012
•
Electrical work for the pedestrian light poles continued this week.
•
Excavation and construction began on the northwest corner of McNary Avenue NW and
Edgewater Street NW. Completion: September 28, 2012
Week of September 17—September 21, 2012
•
Electrical work for the pedestrian light poles will continue this week.
•
Excavation and construction will continue on the northwest corner of McNary Avenue
NW and Edgewater Street NW. Completion: September 28, 2012
•
Excavation and construction of the northwest corner of Gerth Avenue NW and
Edgewater Street NW is scheduled to begin. Completion: September 28, 2012
Week of September 24—September 28, 2012
•
Excavation and construction of the northwest corner of Kingwood Avenue NW and
Edgewater Street NW is scheduled to begin. Completion: September 28, 2012
•
Excavation and construction will continue on the northwest corner of McNary Avenue
NW and Edgewater Street NW. Completion: September 28, 2012
•
Excavation and construction will continue on the northwest corner of Gerth Avenue NW
and Edgewater Street NW. Completion: September 28, 2012
•
Electrical work for the pedestrian light poles will be completed this week.
If you have any questions regarding this project, or have any specific concerns with the traffic
control or safety of the project, please contact Troy Thomson, P.E., Project Manager, at 503-5886211 or [email protected].
SKS/PH:G:\Group\clerical\Projects\cip_rfp_cmgc\710502-2\corr\710502-2_flyer02.doc
 ADA Accommodations Will Be Provided Upon Request 

Documentos relacionados

September 07, 2012

September 07, 2012 555 Liberty Street SE / Room 325 • Salem, OR 97301-3513 • Phone 503-588-6211 • Fax 503-588-6025

Más detalles